Well #4 expected online by April 21.

Reinstallation of the pump and 680 feet of pipe was completed Friday, April 7.  The electrical will be reconnected and a series of tests performed this week.  If all goes well, the well should be back in service “in 1-2 weeks.”

Well #4 shut itself down on January 30 because of an “electro-mechanical problem.”  We have no more information about the nature of the problem.  The repair required removing the roof of the pump house and extracting the pump and 680 feet of pipe.  The work was delayed by continued heavy rains.